设计背景、设计资料、平面布置、装卸工艺、码头结构布置、码头荷载、结构选型、结构计算八个部分。平面布置有平面布置原则、泊位数量的确定、水域以及陆域布置,其中仓库和堆

摘要本次设计的港址位于扬州港西南侧。根据港口地形地质条件、通货能力的要求等,分析采用了高桩码头结构形式。设计主要标准为适用安全经济,设计内容主要包括了港口平面布置以及高桩码头结构内力计算,同时对结构进行必要的稳定性验算,最后对桩基施工工艺进行了简要的说明。 

    本次设计共有设计背景、设计资料、平面布置、装卸工艺、码头结构布置、码头荷载、结构选型、结构计算八个部分。平面布置有平面布置原则、泊位数量的确定、水域以及陆域布置,其中仓库和堆场的面积及分布要根据根据货物量决定。装卸工艺有装卸配备原则、装卸工艺设计和装卸机械数量的确定。码头结构布置有码头结构设计原则和码头结构部分尺寸。结构计算主要是面板、纵梁以及横向排架在荷载下的计算,包括配筋计算和抗裂验算。其中结构内力计算中对可能同时出现在建筑物上的多种荷载,要按照最不利的荷载情况组合。本次设计桩采用钢管桩,同样对桩基承载力也要进行计算和必要验算。62309

毕业论文关键字:高桩码头;集装箱码头;梁板式

   Abstract The design of port site is located in the southwest from yangzhou. According to the requirement of the port of topography and geological conditions, currency ability and so on, the analysis adopted high pile wharf structure form. Design main standards for safe and economic and applicable design content mainly includes the port layout and piled wharf structural internal force calculation, checking to the stability of the structure is necessary at the same time, the last of the pile foundation construction technology were briefly reviewed.

Design background, design data, the design of plane layout, loading and unloading process, structure layout, port load selection, structure calculation, structure of eight parts. Layout layout principles, the number of berths and arrangement for land and water, including the area of the warehouse and yard and distribution according to according to the quantity of goods. Loading and unloading process with loading principle, loading and unloading process design and the number of loading and unloading machinery. Port structure layout has wharf structural design principle and structure section size. Structural calculation mainly panels, longitudinal beam and calculation of the transverse bent frame under the load, including reinforcement calculation and crack resistance calculation. The structure internal force calculation on May appear in a variety of load on the building, at the same time according to the most unfavorable load combination condition. Pile using precast prestressed concrete piles, the design bearing capacity of pile foundation is also necessary to calculate and check.

Keywords: high pile wharf ;container wharf ;beam plate

第一章 设计背景 1

1.1 工程概述 1

1.2 设计原则 1

1.3 设计依据 1

第二章 设计资料 3

2.1 地形条件 3

2.2 气象条件 3

2.3 水文条件 3

第三章 平面布置 5

3.1 设计船型 5

3.2作业条件 5

3.3总体尺寸 5

3.3.1码头泊位长度 5

3.3.2 航道设计尺度 6

3.3.3码头前沿高程 扬州港某3000吨集装箱码头结构规范设计+CAD图纸:http://www.youerw.com/gongcheng/lunwen_68482.html