钢筋混凝土现浇框架结构和煦楼工程施工组织设计

时间:2022-11-06 09:45来源:毕业论文
和煦商业楼的施工组织设计。该工程总建筑面积5438㎡,总高度16m。结构形式是钢筋混凝土现浇框架结构。设计中综合安排施工进度,科学合理调度劳动力,有序使用机械设备,使土建各

摘要施工组织设计是编制出来指导整个施工项目全部过程中各项活动的组织、经济和技术的综合文件。它是工项目管理和施工技术的有机结合,能够保证工程建设开工之后施工活动能够科学、高效和有序进行。85000

本次设计为和煦商业楼的施工组织设计。该工程总建筑面积5438㎡,总高度16m。结构形式是钢筋混凝土现浇框架结构。设计中综合安排施工进度,科学合理调度劳动力,有序使用机械设备,使土建各工种能够密切配合,且各施工段之间交叉流水施工作业。

  此次设计内容包含工程概况和总目标、施工准备、施工部署、土建的施工方、施工进度计划、文明施工措施、安全施工、建筑质量目标保证和建筑工期目标保证等内容。本次设计完成了横道图,网络图,施工平面图等的绘制,具有科学性,针对性和适用性等优点,是确保高速、安全、低耗、优质、文明的重要经济和技术文件。本设计的主要目标是指导施工工作的顺利完成,严格控制工程成本,积极创建优质工程。

毕业论文关键词:施工组织;钢筋混凝土;现浇框架;施工方案 

Abstract  The construction organization design is a comprehensive document of organization, economy and technology, which is the organization, economy and technology of the whole process of the whole construction project。 It is the combination of project management and construction technology, to ensure that the construction activities can be carried out scientifically, efficiently and orderly。

This design is the construction organization design of the HEXU floor。 The project has a total construction area of 5438 square meters, the total height of 16m。Structure form is the reinforced concrete frame structure。 The design of the comprehensive arrangement of the construction schedule, scientific and reasonable scheduling of labor force, orderly use of machinery and equipment, so that the construction of various types of work can be closely matched, and the construction of the cross flow between the construction work。

Including the design of the general situation of the project and the total target, construction deployment, construction preparation, schedule, construction scheme, construction schedule, civilized construction, construction safety, construction quality target guarantee and construction time limit for a project which content。 The design is completed the Gantt chart, network diagram, such as construction plan of rendering, scientific, applicability and advantages of targeted is to ensure high-quality, low cost, safe, civilized, high-speed completion of all construction tasks of important economic and technical documents。 The main goal of this design is to guide the successful completion of the construction work, strict control of the project cost, and actively create quality engineering。

Keywords: construction organization;reinforced concrete,;cast-in-place frame;construction scheme

目录

第一章  绪论 1

  1。1 研究目的与意义 1

  1。2 研究背景 1

  1。3 国内外研究现状 2

    1。3。1 国内研究现状 2

    1。3。2 国外研究现状 2

  1。4 主要研究内容 2

  1。5 项目管理工作流程 3

第二章  工程概况及总目标 5

  2。1 工程概况 5